top of page

Stockton, CA
Domestic Water Phase 2
Public works project involving 340’ of 6” C900, 7659’ OF 8” C900, and 140’ of 12” C900. Misc. valve installation. 3 Jack and Bore sleeves under existing spur line railroad tracks. Traffic control. De-watering. Compaction testing. Asphalt removal and placement. Under dock work. Disinfection and hydrostatic testing.
Client
Port of Stockton
Project Value
$2.5 Million
Completion Date
Dec 2023

bottom of page